GENERAL COLLECTOR OF COCENTAINA DE FONT DE LA PEDRA (ALICANTE)
Direction of the works with the following characteristics: Cocentaina collector: conditioning of the access area to the ravine of fraga. cleaning of the Concentain collector. treatment of leaks by means of a continuous resin sleeve. reconstruction of the bottom of the well fr01. General collector Font de la Pedra: treatment of leaks with continuous sleeve […]
NON-HAZARDOUS WASTE LANDFILL IN ELCHE
Supervision and inspection of the construction works of a waste cell, belonging to the Baix Vinalopó consortium, with a gross capacity of 596,167 m3 (429,240,27 tonnes net of rejections), for an estimated duration of 52 months. The main features of the work have been: Excavation of 68.025 me at the bottom of the pouring cup. […]
DEODORIZATION OF THE MUNICIPAL WASTE TREATMENT PLANTS OF THE VALDEMINGÓMEZ TECHNOLOGICAL PARK
Design and drafting of 5 projects that consisted of the identification of technical improvements available for the minimization of odors of municipal solid waste treatment systems and biomethanization plants integrated in the technology park of Valdemingómez. The measures developed are based on improving the watertightness of vessels, increasing the number of hourly air renewal in […]
SPORTS PAVILION TYPE C
DRAFTING OF THE PROJECT AND DIRECTION OF THE WORKS. According to the needs program provided by the property, it is intended to build a covered pavilion, with a multi-sport court able to be used for the following sports: basketball, handball, volleyball, tennis and indoor soccer. The dimensions and characteristics of the track will meet the […]
WWTP OF PINET (VALENCIA)
Drafting of the preliminary project for construction and operation of the station for a flow of 70 m3/day, 583 h-e, treatment: solid medium-biodiscs
WWTP OF BARXETA (VALENCIA)
Drafting of the preliminary project for construction and operation of the station for a flow of 600 m3/day, 3,000 h-e, treatment of activated sludge, prolonged aeration.
WWTP OF OLIVA
Drafting of the preliminary project of the station for a flow of 17,000 m3/day, 70,833 h-e, treatment of activated sludge, prolonged aeration.
WWTP OF GANDÍA AND SOUTHERN ZONE OF SAFOR (VALENCIA)
Technical assistance to the construction management for the diagnosis and design of the station, with the following characteristics: flow rate of 60,000 m3/day and 143,000 h-e; primary treatment; secondary treatment (using activated sludge); physico-chemical treatment (lamellar decantation); disinfection; chlorination; anaerobic digestion of sludge and biogas line.
PHOTOVOLTAIC INSTALLATION FOR IRRIGATION WELL, FOR THE COMMUNITY OF IRRIGATORS OF HONDÓN-MONOVAR
The purpose of the project is the design of a photovoltaic panels plant capable of producing a power of up to 200 kW, in order to power the well pumping equipment, which is currently connected to the grid. For this purpose, an installation consisting of a photovoltaic panel generator, consisting of 500 panels of 450 […]
CONSTRUCTION PROJECT OF ELECTRICAL UTILIZATION AT THE FOOT OF THE DAM OF ARENÓS RESERVOIR
The purpose of the Project is to describe the construction works for the hydroelectric exploitation at the foot of the dam, of the Arenós reservoir on the Mijares River in the province of Castellón. The main work planned is as follows: – Pipes: includes the installation of a steel pipe with a diameter of 1,550 […]