WORKS BY THE GENERAL COLLECTORS AND WWTP OF NOVELDA AND MONFORTE DEL CID

Detailed description of the project The works consist of the construction of the collector system and a new treatment plant using biological treatment in two stages, for a flow rate of 9,000 m3/day (54,000 inhab-eq). The works include: – Wastewater treatment plant for the towns of Novelda and Monforte del Cid, divided into two treatment […]

TRANSFER PLANT FOR HAZARDOUS AND NON-HAZARDOUS INDUSTRIAL WASTE IN SAGUNTO

The urbanization and development of the industrial estate of Sagunto, with industries related to metallurgy and fuels, among others, is presented as an opportunity for the development of a hazardous and non-hazardous industrial waste transfer center (CTR) close to it, allowing a more economical waste management. The CTR will be located on an area of […]

ZONAL WASTE PLAN OF ZONE XVII OF THE COMPREHENSIVE WASTE PLAN

The work involved monitoring and improving the study of the needs and resources of Zone XVII and its interaction with demography, geology, hydrology, urban planning, transport constraints and protected natural areas, in order to obtain suitable areas for the location of waste recovery and disposal facilities in the region. The analysis and diagnosis of the […]

CONSTRUCTION PROJECT FOR THE IMPROVEMENT WORKS OF THE WWTP OF VORA RIU IN VILA REAL

Detailed description of the project The objectives to be achieved by the Sanitation Entity with the realization of the actions of improvement in the existing WWTP of Vora Riu, are: Expansion of treatment capacity to absorb the growth of the municipality, both urban and industrial. Increased flexibility and guarantees of the purification process. Optimization of […]

ZONAL WASTE PLAN OF ZONE XIV OF THE COMPREHENSIVE WASTE PLAN

The work involved a study of the needs and resources of Zone XIV, as well as their interaction with demography, geology, hydrology, urban planning, transport constraints and protected natural areas, with a view to obtaining suitable indicative areas for the location of waste recovery and disposal facilities in the region. The analysis and diagnosis of […]

PROJECT 2 OF THE NEW WASTE LANDFILL AT THE ESR TREATMENT PLANT IN ELCHE

The work consisted of drafting the Construction Project and the Modified Project for the new operating cell of a municipal solid waste landfill, with an approximate budget of €6,313,925.83. The Elche landfill serves an equivalent population of 325,490 inhabitants, corresponding to the Zonal Waste Plan of Zone XVIII of the Valencian Community. The total approximate […]

SOLID WASTE RECYCLING AND COMPOSTING PLANT AND CONTROLLED WASTE LANDFILL IN ELCHE

The project consists of the construction of a recycling and composting plant for an equivalent population of 325,490 inhabitants and has a budget of approximately €9,308,759.87. The main features of the work are: 50,000 m3 of excavations and 35,000 m3 of landfills. Paving of urban areas with 14.300 m2 of concrete for reinforcement and 65 […]

IMPROVEMENT OF FONT DE LA PEDRA WASTE WATER TREATMENT PLANT

Detailed description of the project Due to the inability of the current plant to treat both the incoming flow and the high pollutant load (discharges from textile industries and mills), the existing facilities need to be renovated/expanded. Furthermore, due to the advanced state of eutrophication in which the Beniarrés reservoir is located, to which the […]

EXTENSION OF ALTEA, CALLOSA D’EN SARRIA, POLOP DE LA MARINA AND LA NUCÍA WWTP

The expansion works of the WWTP consist of the implementation of a new pretreatment, primary settling and biological treatment with nitrification-denitrification, secondary settling, aerobic digestion, thickening and drying of sludge. It has also acted on the equipment and the repair of the civil works of the apparatuses of the existing plant.